Project Description:
Install Cat6 Ethernet cables at client specified locations.
Terminate and connect to client equipment as needed.
Floor Plan - drawing is approximate, not to scale (for jack locations only)
Project Status:
10/7/2013 -
On-site; Site survey; review office space and cabling requirements.
10/10/2013 -
On-site (R,K); 12p-530p; Begin pulling cables to office locations (10/45 cables pulled).
10/12/2013 -
On-site (R,K); 10a-7p; Finish pulling cables to office locations.
10/14/2013 -
On-site (R); 12p-5p; Begin terminations of wall jacks.
10/16/2013 -
On-site (R); 430p-10p; Continue terminations of wall jacks and patch panels.
10/18/2013 -
On-site (R); 10a-4p; Finish patch panel terminations and testing; supply patch cords. All jacks are tested and ready to use <<test results here>>.
10/21/2013 -
On-site (R); 430p-; Install coax RG6-QS cable to extend TWC modem to new location.
11/5/2013 -
On-site (R); Followup visit to assist with general cable cleanup.
Project Photos:
New rack and patch panels -- ready to connect to client equipment.
Wall jacks under desk (see map for locations). Jacks 29-32 pictured.
Ceiling jacks (11,12) for WiFi transmitters.
Project Statistics:
150 feet RG6-QS coax cable (to extend cable modem)
1ea 8RU wall rack installed;
1ea PDU power distribution unit